Scott Dillon
BASc Golf Course Management
Project Description
Directed Field Study #2 - Irrigation System Replacement
Design a new irrigation system suitable for ideal coverage across 3 holes of the Victoria Golf Course property, as well considering all associated project costs, and overall installation timelines tailored to Victoria’s specific and unique needs.
-
Design a new system on software to replace all existing pipe and sprinkler heads with brand new state of the art equipment.
-
Use piping diagrams to effectively size pipe for the property.
-
Complete an installation timeline, working around the specific needs to Victoria’s situation, keeping impact to play low and almost negligible.
-
Compile a full price quote for the installation, encompassing all aspects of the new irrigation system using Google Sheets. Design this budget to be repaid over a series of 5-7 years.
-
Validations:
-
Employer validation letter
-
Complete design displaying coverage using QGIS software
-
Complete database and zone map for all sprinkler heads
-
Summary of labour and part budget for installation
-
Gantt chart for project timelines unique to Victoria’s needs
-
-
Project Updates
Under this heading you will find details pertinent to the completion of this goal. This section will effectively work as a type of blog used in the completion of the first directed field study goal:
DFS 2 - Irrigation System Replacement
Update 1 - Opening Remarks and Parts
As with any new irrigation system installation there are multiple parameters that need to be considered when attempting to design a system that will allow the turf grass to excel for decades to come.
These days, there are multiple upgrades that have been made to installation techniques used by installation companies. These advances have allowed superintendents to trust their irrigation systems like never before. When designing this system, I will be incorporating many new technologies and installation techniques. With the first being the type of sprinkler head.
When irrigation systems were first installed, metal pipes and quick couplers were used by night watermen which had to used in the dark to irrigate the golf course. Under the property of Victoria there are still remnants of the old quick coupler system that was used. Eventually this system wore out and the upgrade was made to new technologies. Installed by Alberta Irrigation in the mid 1980s, was a fully functional 400+ sprinkler head RainBird satellite system, complete with a central control. Currently this system remains in place and does have adequate coverage, but over half of the old RainBird impact sprinkler heads have been replaced with a miss mash of different models of both RainBird and Toro rotors.
The new system will feature what I consider to be the best of both worlds. I believe the RainBird satellite and central control software to be the most comprehensive and user friendly. I believe the Toro Infinity sprinkler heads to be the best for potable water situations, which we are fortunate to find ourselves in at Victoria.
Another topic of discussion within irrigation systems is the type of pipe. Up until about 15 years ago, PVC pipe was essentially the only option for below ground pipe installations. With the destructive Canadian winters, PVC was notorious for cracking, splintering, and spiralling causing massive issues for spring startup. Along came HDPE pipe. This pipe is said to withstand all of the elements a harsh Canadian winter can throw at it. This is made true because any water remaining in the system following blow out, will still freeze, but instead of expanding and blowing the pipe apart, the HDPE actually expands and contracts with the ice. This pipe technology has led to fewer major problems the following year effectively expanding the majority of the systems life span to 50+ years. I felt it crucial to ensure I included HDPE pipe within this new installation plan.
Found below is a complete list of irrigation components to be used;
Irrigation System Components:
-
Wide Area Sprinkler Heads: Toro Infinity 855/835
-
Small Area Sprinkler Heads: Toro T5 Rotors
-
Toro Quick Couplers
-
Lasco Swing Joints
-
RainBird PAR+ES Two Wire Field Controllers
-
HDPE Pipe & Electrofusion Fittings
-
Red and White Gate Valves for Isolation Valves
-
NDS Valve Boxes
Update 2 - Design Software and First Stages
Once all of the desired components have been selected, it is time to design the new installation. For this process I will be using a GIS mapping software called QGIS. This is a sourced based free program for anyone to download and use, but offers a host of powerful tools to use to create, edit, visualize, analyze, and publish geospatial information. This will be the primary tool used for the design of the system.
LINK: QGIS Software
With any GIS software, a high quality digital image of the area will be needed. For this I used Valtus Imagery.
Using the coordinate system designated for the recieved image, I then created an overlay within the GIS software appropriate for the project.
Next, the specific areas of the property were outlined, including greens, tees, fairways, and finally a outline of each specific hole and labeled as such.
Greens are Dark Green,
Fairways are Dark Blue,
Tee Boxes are Yellow, and
Hole Outline is Red
On the property, our water is supplied from the City water system, and because of the location of existing infrastructure, the location of the pump houses must remain in their existing location. These pump houses actually don't contain pumps, only valves. The reason for this being the 36 inch potable water line located approximately twenty-five feet below the golf course's 6th hole.
These aspects can be seen in the images below. Use the arrows to navigate pictures.
Additionally, below is a link to the GIS project files that outline the respective area outlines.

---
Update 3 - Sprinkler Head Placement
When considering where to place sprinklers, I first needed to come up with a game plan for what exactly I wanted to do. The system currently in place does not have any sprinkler heads dedicated to the rough or the greens surrounds. Including these heads in areas necessary will help to reduce the amount of water currently being required by the rough surrounding the greens. Additionally adding complimentary sprinkler heads to the fairway heads for the rough will allow for the precision application of water across the property.
Coverage within these three holes of the replacement system will be head to head coverage, using the industry standard triangular spacing pattern. Using green nozzles which are a mid level distance spray as well as gallons per minute output will allow the irrigation technician on the property to make even further adjustments swapping nozzles larger or smaller where required to meet the turf's specific needs for water or when the golf course undergoes changes in the future. The nozzle performance chart referenced for gallons per minute references as well as how far the sprinkler can throw.
LINK: Toro Infinity 855 Nozzle Performance Chart
Below, the 5th and 6th holes can be seen as well as their desired sprinkler placement. Please note the legend:
-
Green Markers: Greens Sprinkler Heads
-
Red Markers: Greens Surrounds Sprinkler Heads
-
Yellow Markers: Fairway Sprinkler Heads
-
Blue Markers: Rough Sprinkler Heads
-
Orange Markers: Tee Sprinkler Heads
Additionally, a link to the GIS project files that outline the sprinkler head layout with or without sprinkler head spray arcs.
LINK: Sprinkler Head Layout GIS Files (Google Drive Folder)

Update 4 - Piping Diagram and Isolation Valve Placement
Designing a piping system to accommodate a system built to this magnitude will be a feat in its own. When initially determining how to design a piping system, I first had to consider what I wanted to be able to do as the irrigation technician. Currently, when operating the system , I am only able to run stations in pairs, two heads at once on each hole due to a poor layout of the current piping system causing pressure issues. A huge wish of mine would be to run up to triple that on each hole at the same time, while being able to adjust run times for each sprinkler head individually. Additionally, because of the nature of the corporate umbrella the golf course is under, I wanted to "over-kill" design elements, including sizing up pipes slightly larger than what should be needed, to prepare for any possible added features in the property plans.
When laying out the new irrigation piping system, I kept true to standard piping layouts and connected everything in a loop so it would have pressure and flow supplied from both sides of each sprinkler head. I sized the pipe according to PSI friction loss charts ensuring each sprinkler head had enough pressure to operate at the desired 100 PSI.
The currently present irrigation system does not require the addition of a pump house as on our property is fed off a potable 36" mainline that runs deep below the surface of the golf course. While that will remain unchanged, everything allocated to the current golf course infrastructure will be replaced with new updated materials.
Below is a link to the GIS project files that outline the piping system. Isolation valves are included as well in the diagram, allowing for the individual shut off of each hole.
LINK: Piping System and Isolation Valve Layout GIS Files (Google Drive Folder)
Update 5 - Accessories and Satellite Box Placement
Firstly, when considering our current needs for irrigation accessories, the only thing I wanted to ensure was included within the design was a quick coupler for each green location. The greens on the property, are all that really need extra hand watering from time to time. In my four seasons on the property, I have not found the want for a quick coupler on any tee locations. In the future if a quick coupler is needed in an additional location, they are quite easy to install.
When setting the location of the satellite boxes, there was only one wish on my list. I wanted one satellite for each hole, and all three holes in the same location. The location I chose is quite close to the driving range where the power required for the controllers is readily available.
Below is a link to the GIS project files that outline the accessories and satellite locations.
LINK: Quick Coupler and Satellite Box Layout GIS Files (Google Drive Folder)
Update 6 - Wiring Diagram
With wishes similar to the piping system, I knew I wanted individual control sprinkler heads. After thoroughly researching different methods of electrical installations; decoder systems and the RainBird IC control; I decided to go with an "old school" method of two wire control. For the scope of the installation, and because this installation plan is only encompassing three holes of the golf course, I thought this would be the easiest way to integrate the entire system with a future central control. Two wire systems don't seem to be going anywhere in the near future.
When designing this system, I tried to route the wire the shortest distance possible back to the controller. Each head has a power wire and a common wire. The common wire is run in a giant circuit beginning at the controller and ending at the last sprinkler head on each hole.
Below is a link to the GIS project files that outline the wiring diagram.
LINK: Wiring Diagram GIS Files (Google Drive Folder)
Update 7 - Installation Plan and Equipment Requirements
Within this section, the equipment requirements will be explained as well as the installation techniques used will be outlined.
At Victoria Golf Course, we are one of the busiest golf courses in Canada, operating under the City of Edmonton we are mandated to create conditions for consistent golf every day we can. In order to have as low of an impact on play as possible, most of this installation would be completed overnight. This will allow the golf course to remain open during the day, as well as create a safety barrier for the irrigation installers. The steps outlined below are tailored to keep these goals in mind as well as respect various noise bylaws imposed on our property by the City.
For the installation of this system, I have decided to dig trenches for all pipe instead of pulling. This option was decided for a couple reasons;
-
Pulled pipe has the potential to be cut or gouged by rocks under the surface.
-
Victoria Golf Course has areas under the surface that have been filled with some rocky material. Because these areas are unmarked and random, the reliability of pulling any pipe, and wiring can be risky.
-
-
Trenched lines will allow for wiring to be run with pipe more efficiently.
-
Victoria Golf Course would likely not get funding for another replacement system for at least another fifty years, so ensuring the installation goes perfectly by visually inspecting while under pressure all aspects prior to backfilling will allow for the maximum lifespan of the newly installed system.
Step 1: Alberta One Call and Site Marking
Step one will be one of the few steps done in the daylight. Alberta One Call will come out to mark any underground utilities that need to be avoided. If there are no blocks to the design of the system, the design can then be drawn out using turf paint and marking flags. Working at a pace of one hole per night, the area will be marked by the project manager during the day before the scheduled night work is to begin.
Step 2a: Sod Cutting and Trenching 6" Mainline
The first step in the construction of this new system is installing the new 6" line that will serve as the main source for this area's (5,6 and 7) irrigation water. This line will be tied in with the existing 8" main line that runs the distance of the entire property.
The area will first be sod cutted and the sod will be removed neatly and placed to the side. The trencher will then follow behind, and behind the trencher the 6" pipe will be pulled out and laid into the trench. After the pipe is laid, the t's will be installed and fused for the future connections of the 4" line.
The majority of the trench will be then buried into the ground and the area will be compacted around the pipe before sodding.
Step 2b: Sod Cutting and Trenching 4" Lateral
Once play for the day has winded down, the first working step in the installation process can begin; sod cutting. The sod cutter will remove the sod from all areas where sprinkler heads and pipelines are to be placed. The sod will all be saved, rolled neatly, and placed to the side of the hole approximately 15 feet away.
When sod cutting, the first area to be cut will be the lateral lines running from the mainline to the desired hole of work. (In the case of hole 5, these two lines will be cut across the 6th fairway.)
Once the sod has been cut from the mainline to the hole of work, the lateral line will be trenched in. This excavation will remain open until the wiring has been completed.
Step 3: Trenching Irrigation Pipelines, Laying 4" Lateral and Tying in with 6" Mainline
Using the trencher, all 3" and smaller pipelines will be completed as per the project plan. The operator will be careful using this machine and plywood will be utilized to distribute the weight of the trencher to avoid any additional turf loss along the way.
Elsewhere, the 4" Lateral line will be placed into the trench and will be tied into the 6" line that takes off from the 8" mainline. There will be an isolation valve installed after each connection to the 6" line has been completed. Once the fusion joints have effectively cooled down the isolation valve can be backfilled and installed in a valve box. Space for the irrigation wire bundle should remain.
Step 4: Laying 3" Pipe
Once the trenching has begun, following closely behind will be the pipe. Installed on a pipe rack, the lines will be pulled into the trenches using a workman or similar machine. Where necessary the pipe will be held down using a cinderblock or similar heavy material. Once trenching is completed and the pipe is all completely laid, the next step can begin.
Step 5: HDPE ElectroFusion, Running Wire
Using the HDPE ElectroFusion machine, all necessary joints will be electro-fused and given time to cool and solidify. While this is occurring, each sprinkler head location will have a saddle fitting installed onto the 3" line.
Wire will also begin to be spooled out at this time. One power wire will be run to each sprinkler head and all the way back to the controller. Ideally they should be marked with where the wire is running to, however this can always be determined later at the satellite controller. 6-8 feet of extra wire should be left at the controller for each power wire. The common wire will also be run at this time. When running wire, WHITE wire will be used for the common, and RED will be used for the power wires. Service loops of wire (approx. 2 feet coiled) should be left at each sprinkler head hole as well to allow for future changes or upgrades.
Step 6: Sprinkler Head Installation and Wiring and Backfilling 4" Lateral and Re-Sodding Area
Once the saddles are installed onto the 3" pipe, a team of installers should begin installing sprinkler heads. This includes the swing joint at each head as well as the completion of the wiring.
Additionally at this time, the 4" lateral can be backfilled, compacted using tampers and re-sodded. Special care should be taken to level the valve box concealing the isolation valve to ensure it is level with the surrounding area.
Step 7: Pressurize, Level Sprinkler Heads, Backfill and Compact
After all sprinkler heads are installed, the system will be pressurized for the first time and the system will be inspected for leaks. Any issues will be resolved. Once the system is holding water as expected, the sprinkler heads will need to be levelled, backfilled and compacted. Sprinkler heads should be level with the ground, installed no more than 1/2" below the surface. Carefully hand tamping around the swing joint and head will ensure effective compaction. Care should be taken to ensure enough space for the sod remains.
Step 8: Backfill and Compact Irrigation Lines
While one team is backfilling around sprinkler heads, another larger team can start on the rest of the pipe. Hand tamping around the pipe up to the surface is important. Care should be taken along these areas to ensure enough space for the sod remains.
Step 9: Re-sod Irrigation Lines and New Sprinkler Heads
The next step in the irrigation install is sodding. All team members will sod the affected areas carefully. Care should be taken to ensure there are no massive dips or holes beneath the sod, effectively returning the area back to as it was before the installation began. The use of a turf roller will be implemented to smooth out any imperfections in the sod job.
Step 10: Wire Sprinkler Heads into Controller
While the sodding is taking place, a single member of the installation team will begin wiring the new sprinklers into their respective controllers. A rough database will be established at this time as well.
Step 11: Site Marking and Securing Open Trenches
Once work is completed for the night, the site will be marked with pin flags, marking all sodded locations and signs will be placed at the tee explaining to golfers to attempt to avoid driving on these areas. Free drops will also be provided to these players that land on affected areas. The pin flags will be maintained in place for approximately one week of play while the sod re-establishes. Turf mowing can continue once these pin flags are removed. Remaining open trenches (6" line while 5 and 6 holes are completed) will be secured with plywood for golfer safety during the day.
Step 12: System Testing
Once the sodding is completed, the controller is wired, and the site is marked, the final step before completion is system testing. This is the first time a full system test will be completed and a couple of minor issues are to be expected. These will be fixed as they appear.
Step 13: Repeat
The installation procedure outlined above will be practically identical to what is to be expected for all three holes. Safety is the major concern and any open holes after the work is completed for the night will be secured and visibly marked.
Step 14: Project Completion
After a successful system test has been completed, the irrigation system is ready for use. Sprinkler heads from the old system will be removed at a later date by the irrigation technician present on the property.
LINK: Installation Procedure
Installation Equipment:
Having recently undergone a previous irrigation addition to the property, the irrigation equipment will be quite similar to what has been used before. Below is the list of equipment and links to the exact model I would use.
-
Equipment List:
Update 8 - Project Timelines and Gantt Chart
When installing a project of this magnitude, it is important to remain vigilant when planning staffing to ensure the project is installed as efficiently as possible.
The link below can be used to view the project's gantt chart which displays all projects steps, short descriptions, estimated number of employees and estimated time of completion for each step.
LINK: Irrigation Installation Gantt Chart and Man Power Projections

Update 9 - Project Costs
Listed below is a link to the project costs spreadsheet. Within this tool you will find the anticipated components costs, the labour costs and the equipment costs. Also included is the 10% project contingency fund. When determining component costs, I called multiple distributors and irrigation companies for their knowledge and pricing of the components shown in the spreadsheet which is linked below.
LINK: Irrigation Installation Costs
Update 10 - Final Remarks and Closing
I’ll have to admit, when I first designed this Directed Field Study, I had originally planned to do a complete system for all 18 holes and additional areas of the property. I can say will full certainty, a project of that magnitude is not a one person job, so the revision to just completing 3 holes was a definite benefit in this project’s completion.
When designing this system, I used a combination of a couple different mentalities found in and out of the irrigation industry. I combined an idea from Ian Morrow with the double row of sprinkler heads on the edge of a fairway to water specifically the rough or the fairway with the traditional head to head coverage in a triangular pattern to allow for the efficient use of water. The sprinkler heads were all distanced based on a mid range nozzle to allow for changes in water requirements, and they were all wired using the two wire system, but wired individually for precision control. The biggest upgrade was definitely the piping technology. By installing HDPE pipe and using ElectroFusion technology everywhere possible, the functionality of this system should be guaranteed for an extensive period of time, outlasting any new PVC system. Additionally, although this was only a three hole irrigation system upgrade, the controller chosen will allow for the future possibility of a central control. Through all of these parameters, I feel I have designed the ideal system for the longevity of the golf course and have prepared us for becoming environmentally responsible for the amount of water used on the property.
Apart from the design, another interesting learning note was the sheer amount of technology available within the golf course irrigation world. A great example of this would be the ElectroFusion technology for HDPE pipe fusing. Essentially ElectroFusion is a much more reliable and efficient way of installing HDPE piping. The two sections of pipe are joined together with a specialized fitting with a unique barcode of the pipe’s requirements for a positive fusion. Two wires running from the fusion machine are attached to this fitting and the barcode is scanned and the machine does the rest. The fitting is heated for the specific amount of time required by the manufacturer, is then cooled and finally pressure tested for a positive fusion of the pipe feature.
Another technological advance is the Toro Infinity sprinkler head. For the past 3 seasons at Victoria, I have been installing these sprinklers around the property and honestly, right now I do not see a better sprinkler head in the industry. These sprinkler heads are installed like any other sprinkler, but have a cavity to support the wiring and any future upgrades Toro decides to come out with in the future. This sprinkler head is said to be “future-proof” and for that reason is my choice of sprinkler head.
The knowledge gained through this Directed Field Study will continue to serve me well in the future. Using the techniques and skills developed through this DFS, I do feel comfortable designing a system of this magnitude or larger in the future, and with a team of installers, I feel I would be able to effectively install the designed system effectively.
While changes in my personal professionalism are not dramatic, the ability to design an irrigation system will undoubtedly be beneficial to a golf course. From my understanding and what Victoria has gone though in the past, the design of a new irrigation system is a MAJOR portion of the overall project cost. By being able to do the entire design and installation in house, the potential for tens of thousands of dollars in savings will benefit the property exponentially.
Updating my personal knowledge of technology within this space will serve useful even when I continue to work to maintain the current system at Victoria. Unfortunately, working for a corporation as large as the City of Edmonton, the installation of a new irrigation system is very unlikely. The sheer cost of a project that scale will take a very long time to receive funding for. Using some of these new technologies I have learnt about will help to upgrade the system in specific areas to make it last as long as it possibly can.
Completed Project
Use the links below to view the completed project file in your desired format;
LINK: DFS 2 - Irrigation System Replacement
-
Google Docs LINK: DFS 2 - Irrigation System Replacement
-
Microsoft Word LINK: DFS 2 - Irrigation System Replacement
-
PDF LINK: DFS 2 - Irrigation System Replacement
Project Validations
LINK: Employer Validation Letter
LINK: New Installation Holes 5,6,7 - GIS Project Files (Google Drive Folder)
LINK: New Installation Holes 5,6,7 - Installation Procedure
LINK: New Installation Holes 5,6,7 - Gantt Chart and Man Power Matrix
